Write the measurement model, list every input, evaluate each as a standard uncertainty, apply sensitivity coefficients, combine in quadrature, expand with k. Eight steps, one table.
The eight steps
- 1. State the measurand precisely: e.g. the correction to the indicated temperature of the unit under test at 5 °C.
- 2. Write the model: correction = t_ref + δt_ref_drift + δt_bath_gradient + δt_bath_stability − t_uut − δt_uut_resolution … each δ a correction with an expected value of zero and an uncertainty.
- 3. List the inputs and gather information: certificate uncertainties, specifications, repeatability data, resolutions.
- 4. Evaluate each as a standard uncertainty (Type A from data; Type B from limits with a distribution).
- 5. Determine sensitivity coefficients from the model.
- 6. Combine: u_c² = Σ (c_i u_i)².
- 7. Check effective degrees of freedom if any Type A component is based on few observations.
- 8. Expand: U = k u_c, usually k = 2, and report with the value rounded consistently.
A minimal temperature example
Reference certificate 0.02 °C (k=2 → 0.010); reference drift ±0.01 (rect → 0.0058); bath gradient ±0.02 (rect → 0.0115); bath stability observed SD 0.008; UUT resolution 0.1 (rect → 0.0289); UUT repeatability 0.012. Combined ≈ 0.035 °C; U ≈ 0.07 °C at k = 2. The resolution term dominates — a common finding for 0.1 °C loggers.
Frequently asked questions
- How many components should a budget have?
- As many as the model needs and no more. Six to twelve is typical for a temperature calibration; a budget with fifty components usually double-counts.
- Should I include components that are negligible?
- List them with their evaluated values so the reviewer can see they were considered; they will contribute nothing to the combined value.
References
- [1]JCGM 100:2008 — Guide to the expression of uncertainty in measurement (GUM)
- [2]EA-4/02 M: Evaluation of the Uncertainty of Measurement in Calibration
General technical guidance written against the cited sources. It is not regulatory or legal advice and does not replace the applicable standard, guideline or a qualified reviewer's judgement.
Have a question on this topic?
Ask ValiTrac AI and see the evidence and calculation behind the answer.
Ask ValiTrac AIFree calculator: Uncertainty budget
Combine Type A and Type B components per the GUM: divisors by distribution, sensitivity coefficients, u_c, effective degrees of freedom and U at k = 2.
Open the calculatorMetrology on ValiTrac
Measurement science, traceability, uncertainty and technical evidence.
Ask a metrology questionRelated articles
Type A vs Type B uncertainty evaluation
Type A uses statistics on repeated observations; Type B uses any other information. Both produce standard uncertainties that combine the same way.
The reference thermometer's contribution to uncertainty
The reference contributes its certificate uncertainty, its drift since calibration, and any interpolation or self-heating effects. Together they set the floor of what can be claimed.